Site Re-development
The project entailed the demolition of the existing dilapidated substation site and construction of a new primary distribution substation compound. Earthworks were undertaken to re-profile the existing tiered site and form a new flat level compound area, before constructing a new 33/11kV switch building and bunded transformer foundations.
- Site Establishment
- Demolition of the Existing Below Ground Foundations
- Cut & Fill Earthworks to Form New Engineered Platform
- Construction of New 33/11kV Switchbuilding
- Construction of New Transformer T1 & T2 Bunded Foundations
- Underground Surface Water and Foul Drainage Systems Including Cess Tank Installation
- Underground Cable Ducting and Drawpit Systems
- Underground Earthing Systems
- New Perimeter Security Palisade Fencing and Gates
- Tarmac Roads